Chennai: Port-Maduravoyal Expressway Corridor Project Halted Again, Details Inside – News18

Chennai: Port-Maduravoyal Expressway Corridor Project Halted Again, Details Inside – News18
Share

Last Updated:

Chennai’s Rs 5,885 Crore Expressway Project Hits Another Roadblock. (Photo: The Indian Express)

The National Green Tribunal is now reviewing the project, which has already faced a decade of delays. The next hearing is set for July 26.

The stalled Chennai port to Maduravoyal elevated expressway project, which was initiated in 2009, began construction in January this year.

But, as per recent developments, the construction work has been put to a halt again.

According to TOI, the National Highways Authority of India’s (NHAI) Rs 5,885-crore port-expressway corridor is in trouble after the Tamil Nadu Water Resources Department (TN WRD) directed the central agency to halt ongoing Cooum river work. They also The National Green Tribunal is now reviewing the project, which has already faced a decade of delays. The next hearing is set for July 26.filed complaints in at least four police stations around the city. In addition, a case is underway before the National Green Tribunal (NGT).

The project came under fire after NHAI began dumping rubble into the Cooum River to create access for its rig machinery. As per studies, if Cooum’s flow is restricted in this manner, hitherto untouched neighbourhoods in Chennai may also be flooded during the monsoon.

On May 28, WRD authorities, led by its chief engineer, met with NHAI officials, requesting a formal commitment from the highway body to restore the river after construction, collaborate in flood response, redress damages and protect public safety. “The project has been stopped now. Only after the NHAI provides an undertaking in a ‘bond’ can the project proceed. They have agreed to give the undertaking in two days,” WRD chief engineer S Ashokan told The Times of India.

According to Ashokan, NHAI must fund the whole cost of implementing flood response recommendations from Anna University’s Centre for Water Resources, as well as restore the river to its former width to compensate for the pillars’ area used. “They have agreed to all the conditions,” he added. The water resource department also filed police complaints against NHAI at several stations within the 20.9-kilometre corridor jurisdiction.

The National Green Tribunal (NGT) is currently reviewing the expressway project, which has already been delayed by a decade and the next hearing on this matter is scheduled for July 26.



Source


Share

Related post

MoRTH’s Dedicated Cell to Review Detailed Project Reports for Timely Completion of National Highways – News18

MoRTH’s Dedicated Cell to Review Detailed Project Reports…

Share The DPR is an essential component for the successful implementation of a national highway project and includes…
Declogging, weeding and repair of drains and canals to begin soon in Andhra Pradesh

Declogging, weeding and repair of drains and canals…

Share A portion of Eluru Canal infested with water hyacinth in Vijayawada. | Photo Credit: K.V.S. GIRI The…
Kabir Singh Star Nikita Dutta Purchases New-Gen Mercedes-Benz GLC Worth Rs 74 lakh – News18

Kabir Singh Star Nikita Dutta Purchases New-Gen Mercedes-Benz…

Share Nikita Dutta chose the spotless black colour for her new Mercedes-Benz GLC, the brand’s best-selling SUV in…